Screw piles and the Building Code

How screw pile foundations fit with consents, engineering and sign-off in New Zealand.

An engineered foundation

NZS 3604, the standard most timber-framed houses are built to, covers timber and concrete piles but not screw piles. So screw pile foundations are a specific engineering design: an engineer designs them for the building and the site, and that's how they meet the Building Code, under clauses B1 (Structure) and B2 (Durability).

A floor plan on a table with a tape measure and a pen
Screw pile foundations are designed by an engineer for each building and site.

Producer statements

For consented work, councils rely on producer statements:

  • PS1, design: the engineer's statement that the design meets the Building Code. It goes in with the consent application.
  • PS2, design review: another engineer's check of the design, when council asks for one.
  • PS3, construction: our statement that the piles were installed to the design, with the torque records.
  • PS4, construction review: the engineer's statement that they've reviewed the installation.
Producer statements in order: PS1 design by the engineer and PS2 design review if council asks, with the consent application; then PS3 construction from us with the torque records, and PS4 construction review by the engineer, after the piles are installed PS1 Design The engineer PS2 Design review Another engineer, if council asks PS3 Construction Us, with the torque records PS4 Construction review The engineer With the consent application After the piles are in
The paperwork for consented work, in order. PS2 is only needed when council asks for it.

Consent, or exempt?

Whether you need a building consent depends on what you're building, not on the foundation. Many small decks, sheds, sleepouts, carports and pergolas are exempt under Schedule 1 of the Building Act if they meet its conditions, and from 2026 so are small standalone homes up to 70m². Houses, extensions and most relocated homes need consent.

Exempt work still has to meet the Building Code, so the piles still need to suit the structure. Your designer or council has the final say on whether you need consent.

Inspections

Council may want to inspect the piles before the floor goes on. Because screw piles are ready as soon as they're in, that inspection can happen as soon as we finish.

Working with your engineer

Already have an engineer? We'll install to their design and give them what they need for sign-off. If you don't, we can organise the engineering for you.

Get a free quote

Got a site? Let's get it piled.